Part A - Framework conditions 
11 
Any additional marine environmental protection measures which are later found to be neces 
sary on the basis of latest findings and/or the results of operation-phase monitoring shall be 
included in a suitable way in the monitoring schedule. 
11 Cluster study 
As far as different construction sites/projects take place in regional and temporal conjunction, 
the project surveys shall be conducted conjointly (cluster study). 
However, the surveys for the features of conservation interest benthos and fish are to be con 
ducted individually within the respective project areas. The reference areas may be used by 
one or conjointly by several project contractors (Section 12.2.1). 
12 Assessment region 
The assessment region is the total area in which the studies according to the StUK are carried 
out. It is comprised of the assessment area (including the project area) and the reference 
area. 
The scope of assessment (methodology, purpose, and duration) in the assessment area shall 
not exceed applicable state-of-the-art scientific and technical requirements. The individual 
features of conservation interest require different assessment areas in terms of size and loca 
tion. If legal or factual circumstances are such that the standard size of assessment areas as 
defined below appears to be inadequate or unsuitable, such assessment areas shall be 
adjusted to local conditions by the planning approval/approval authority. 
12.1 Project area and assessment area 
The project area is the area designated for the construction of the wind farm and defined by 
the respective coordinates as given in the application papers, without inclusion of a sub 
sequent safety zone. 
The assessment area comprises the project area and, depending on the individual features of 
conservation interest, surrounding areas that are required for the professional investigation of 
a given feature of conservation interest. 
12.1.1 Benthos/fish 
The size of the assessment area corresponds to the current size and location of the wind 
farm.
	        
Waiting...

Nutzerhinweis

Sehr geehrte Benutzerin, sehr geehrter Benutzer,

aufgrund der aktuellen Entwicklungen in der Webtechnologie, die im Goobi viewer verwendet wird, unterstützt die Software den von Ihnen verwendeten Browser nicht mehr.

Bitte benutzen Sie einen der folgenden Browser, um diese Seite korrekt darstellen zu können.

Vielen Dank für Ihr Verständnis.