26
Part B - Certificates and approval requirements
During installation, the logistics of all significant components and assemblies shall be presented and
certified from the production location to the installation site in order to exclude dangers to personnel and
risks to equipment and the environment.
• Planning documents
The manufacturer of the components shall provide complete drawings, specifications and instruc
tions for the installation procedure as well as installation and erection of the wind turbine. The manu
facturer shall supply details of all loads and weights with data on the centre of gravity, lashing points,
special tools and processes necessary for lashing and installing the components.
• Takeover of the components
Components shall be moved and stored during installation and transport in accordance with the
manufacturer's instructions. Components shall be secured where there is a risk of movement and
damage by wind, swell, etc.
• Climatic conditions
The climatic limits specified by the manufacturer shall be observed and maintained during installa
tion. The following points shall be taken into account, amongst others:
Swell (wave heights),
Tides
Wind speeds
Visibility
Temperature
Rain
Lightning
Snow and ice
• Certification of the transport and installation concept
The manufacturer of the structures shall be adequately described and it shall be possible to test it with
regard to feasibility of undertaking it at sea. Any danger to public safety and shipping shall be excluded.
Certifications of the significant construction phases for transport and installation in order to undertake
the planned project shall be described adequately with the following sub-items, amongst others:
Construction phase plan
Ancillary equipment and resources
Arrangement of marine vessels, buoys, lights, etc.
Lifting, lowering, unloading and ballasting procedures
Inspection of the seabed condition
Necessary static and dynamic certificates for performing the lifting and installation procedures
Regulation of responsibilities and communication priorities in all important transport and instal
lation procedures and
Certification of the equipment involved such as cranes and derrick barges
• Towing procedures and installation
The following certificates, amongst others, shall be provided for towing and transport procedures as
well as installation:
Buoyancy of the construction, which shall take account of not only vertical and horizontal move
ment but also the transition from floating condition
adequate buoyant force and sufficient distance from the base of the body of water, as well as
certification of sufficient bollard pulling force.
• Access to the installation site
The installation site as well as all routes leading to it shall be secured. The following points shall be
taken into account, amongst others:
Load capacity of the equipment
Access ways to the installation site