Part  B  -  Certificates  and  approval  requirements

2  General
Considering  the  overall  system  of  an  offshore  wind  turbine  formed  by  the  support  structure  and  turbine ­
  as  well  as  of  the  overall  system  of  an  offshore  wind  farm  formed  by  the  offshore  wind  turbines,
cabling  within  the  wind  farm,  submarine  cables,  transformer  substation  and  any  additional  elements,
evidence  should  be  provided  that  the  already  type-certified  turbine  together  with  the  design  of  the
support  structure  for  the  specific  site  and  any  of  the  aforementioned  components  of  the  offshore  wind
park  are  in  accordance  with  the  applicable  certification  directives.  As  such,  the  external  conditions  of
the  specific  site  (soil  conditions,  wind  and  wave  distribution,  tides,  ice  drift,  stability  of  the  electrical
grid,  wind  farm  configuration)  and  special  features  shall  be  considered.
Furthermore,  independent  inspection  of  the  implementation  (production,  transport,  installation  and  commissioning) ­
  shall  guarantee  that  the  turbine,  support  structure,  cabling  within  the  farm,  submarine  cables, ­
  transformer  substation  and  any  other  components  of  the  offshore  wind  park  are  in  accordance  with
the  certified/tested  implementation  documents  and  do  not  reveal  any  serious  defects  or  damage.
Periodical  inspections  shall  be  made  to  inspect  the  status  of  the  offshore  wind  farm  during  the  operating ­
  phase.  Periodical  inspections  are  required  in  order  to  maintain  the  operating  permit.
In  all  of  the  (component)  certificates  listed  below,  it  is  necessary  to  check  whether  the  certificate  or
at  least  parts  of  it  are  to  be  obtained  on  the  overall  mechanical  system.  This  is  the  case,  for  example,
when  measuring  and  checking  the  natural  frequencies  of  the  offshore  wind  farm.
The  test  procedure  principally  includes  the  following  elements  and  steps:
1)  Type  certificate  for  the  turbine;
2)  Test  of  the  site  conditions  including  soil  properties  (site  evaluation);
3)  Test  of  the  site-specific  loading  assumptions  and  the  support  structure  (site-specific  design  evaluation); ­
  Test  whether  the  type  certificate  (1)  of  the  turbine  covers  all  site  conditions,  otherwise  a  supplementary ­
  test  of  the  turbine;
4)  Certificate  of  conformity/test  certificate  for  the  site-specific  design  of  the  offshore  wind  turbine
following  completion  of  points  (1)  to  (3);
5)  Test  and  evaluation  of  the  facilities  for  inspecting  the  offshore  wind  turbines  as  an  overall  system
(Supervisory  Control  and  Data  Acquisition,  SCADA,  including  the  Condition  inspection  System,  CMS);
6)  Testing  and  evaluation  of  sea  operations  and  the  decommissioning  concept;
7)  Production  inspection;
8)  Inspection  of  transport,  installation  and  commissioning;
9)  Certificate  of  conformity/test  certificate  for  the  inspection  services  following  completion  of  points
(5)  to  (7);
10)  Project  certificate;
11)  Periodical  inspections  for  maintaining  the  test  certificate  and  the  operating  permit;
12)  Testing  and  inspection  of  the  decommissioning  and  issue  of  the  associated  test  certificate/certificate ­
  of  conformity.
As  a  rule,  the  type  certification  is  applied  for  by  the  manufacturer  of  offshore  wind  turbines.  Registered ­
  inspectors  shall  be  accredited  by  the  BSH  on  a  case-by-case  basis.  It  is  highly  recommended  for
registered  inspectors  to  be  involved  and  accredited  at  an  early  stage,  as  well  as  the  information  exchange ­
  with  the  certifier/registered  inspector  to  commence  as  soon  as  possible.
Definition  of  the  site  conditions  including  the  soil  situation  and  of  the  directives  and  methods  to  be  used  in
the  design  basis  (principles  for  positioning)  should  be  agreed  at  an  early  stage  with  the  certifier/registered
inspector  in  order  to  avoid  problems  during  the  subsequent  phases  of  detailed  design  and  evaluation.
A  (pre-)evaluation  of  the  assumptions  and,  if  necessary  of  the  specified  design,  by  the  certifier/registered ­
  inspector  is  recommended  as  part  of  the  preparation  of  tender  documents  for  a  bidding  process.
            
Waiting...

Nutzerhinweis

Sehr geehrte Benutzerin, sehr geehrter Benutzer,

aufgrund der aktuellen Entwicklungen in der Webtechnologie, die im Goobi viewer verwendet wird, unterstützt die Software den von Ihnen verwendeten Browser nicht mehr.

Bitte benutzen Sie einen der folgenden Browser, um diese Seite korrekt darstellen zu können.

Vielen Dank für Ihr Verständnis.