88
Part B - Verifications and approval requirements
If tests on high-voltage submarine cables cannot be performed in accordance with the afore
mentioned standards, reference is made to the CIGRE recommendations in their current ver
sion, published in the following issues of Electra (CIGRE in-house journal):
• CIGRE: Recommendations for Mechanical Testing of Submarine Cables. Electra Vol. 171,
1997.
• CIGRE: Recommendations for Testing of Long AC Submarine Cables with Extruded Insula
tion for System Voltage above 30 (36) to 150 (170) kV. Electra Vol. 189, April 2000.
• CIGRE: TB 490, Recommendations for Testing of Long AC Submarine Cables with Extru
ded Insulation for System Voltages above 30(36) to 500(550) kV.
6.2.2.2 Direct current transmission
The current version of the following CIGRE recommendation can be used for all direct current
(DC) cables:
• CIGRE Recommendations for Mechanical Testing of Submarine Cables. Electra Vol. 171,
1997.
The following CIGRE recommendations in their current version can be used for plastic-insu
lated high-voltage direct current (HVDC) cables:
• CIGRE: Recommendations for Testing DC Extruded Cable Systems for Power Transmission
at a Rated Voltage up to 250 kV. Electra Vol. 206, 2000.
• CIGRE: TB 496, Recommendations for Testing DC Extruded Cable Systems for Power
Transmission at a Rated Voltage up to 500 kV.
The following CIGRE recommendation can be used for cables with mass-impregnated pa
per insulation:
• CIGRE: Recommendations for Tests of Power Transmission DC Cables for Rated Voltages
up to 800 kV. Electra Vol. 218, 2005.
6.3 Documents to be submitted for the approval
The following documents must be submitted 6 months before the start of the cable laying at
the latest:
[Doc. No. 610] Technical description of the cables: incl. specifications of the cables, junction
boxes, crossing constructions, laying equipment
[Doc. No. 611] Burial Assessment Study (BAS): On the basis of the evaluated results of the
cable route survey (please refer to the Standard Ground Investigations,
Part D) for the model of laying equipment which is actually available
(so-called Installer BAS)
The following documents must be submitted 3 months before the start of the cable laying at
the latest:
[Doc. No. 612] Construction plan incl. preparatory measures for the construction (e. g. pre
lay grapnel run, laying of a mattress when building crossing constructions)
[Doc. No. 613] Detailed description of the cable-laying procedure
As part of the approval procedure, BSH reserves the right to demand further verifications that
the stipulated minimum burial depth is achieved.