Volltext : Standard Design

86

Part  B  -  Verifications  and  approval  requirements

5.5.4  Documents  to  be  submitted  to  maintain  the  operating  permit
[Doc.  No.  550]  Annual,  summarising  verification  report  of  the  appointed  inspector  (monitoring ­
  report  -  summary  of  the  results  of  the  periodic  inspections,  please  refer
to  chapters  B1.3.5  and  B2.5.3),
[Doc.  No.  551]  Annual  certificate  of  conformity  for  the  test  and  inspection  plan  for  the  periodic ­
  inspections,  which  is  compiled  on  the  basis  of  the  verification  report  in
accordance  with  Doc.  No.  550.

5.6  Decommissioning
The  requirements  for  decommissioning  are  regulated  in  chapter  B2.6.
            
Waiting...

Nutzerhinweis

Sehr geehrte Benutzerin, sehr geehrter Benutzer,

aufgrund der aktuellen Entwicklungen in der Webtechnologie, die im Goobi viewer verwendet wird, unterstützt die Software den von Ihnen verwendeten Browser nicht mehr.

Bitte benutzen Sie einen der folgenden Browser, um diese Seite korrekt darstellen zu können.

Vielen Dank für Ihr Verständnis.