Part B - Verifications and approval requirements
75
4.5.2 Documents to be submitted when applying for an extension of the operating per
mit
[Doc. No. 450] Annual verification report by the appointed inspector summarising all the
RNAs (summary of the results of the periodic inspections, please refer to
chapters B1.3.5 and B2.5.3)
[Doc. No. 452] Certificate of conformity pertaining to the operation of all the RNAs at the
wind farm (incl. the periodic inspections).
4.6 Decommissioning phase
The requirements pertaining to decommissioning are specified in chapter B2.6.