50
Part B - Verifications and approval requirements
2.4.2.3 As-built report
Once the installation phase has been completed, the as-built status shall be accordingly doc
umented. This shall include a representation summarising all the major deviations from the
approved documentation that have an effect on the structural integrity of the overall structure,
incl. geometric deviations (site, incline, tolerances, shock), structural deviations (e. g. addi
tional intermediate elements), deviations in production, grouting etc.
2.4.3 Documents to be submitted when applying for operating release
The following documents shall be included with the documentation for applying for operating
release:
[Doc. No. 240] Inspection reports and certificate of conformity pertaining to
- The monitoring of the production phase
- The monitoring of transport and the installation phase as well as
- The monitoring of the commissioning phase.
[Doc. No. 241] Corrosion protection - verification confirming that implementation (applica
tion) has been carried out properly and that the quality of the processing cor
responds to the requirements
Verification may be performed based on acceptance procedures according
to DIN EN ISO 12944-8, incl. the Appendix thereto (form), resp. in accordance
with the respective Additional Technical terms of Contract (ZTV).
[Doc. No. 242] Verification report of the appointed inspector pertaining to Doc. No. 241,
based on the verification reports supplied by the approval holder in ac
cordance with DIN 10204
[Doc. No. 243] As-built report
[Doc. No. 244] Verification report pertaining to Doc. No. 243
[Doc. No. 245] Operations manual
This document shall contain a description of at least the following points in a
plausible and transparent manner:
- General sequence of operations
- Communication flows
- Monitoring of the offshore wind farm
- Monitoring of the offshore station for the substation as well as the grid con
nection within the farm
- Monitoring of the offshore converter station and the power export cable
- Maintenance and repair concepts.
[Doc. No. 246] Verification report pertaining to Doc. No. 245
When operation commences, the appointed inspector shall make sure that
the content of the operations manual is correct and that all processes are
being carried out correctly. This shall be accordingly documented in the veri
fication report.
[Doc. No. 247] Concept for the periodic inspections, incl. test and inspection plan
The concept for the periodic inspections, incl. the test and inspection plan
shall be submitted no later than 3 months following the trial operation of the