10
Part A - Introduction
Execution
Erection
- Production of the
foundation elements;
- Inspection of the
ground conditions
with regard to consistency
with the
design; inspection
of production of the
foundation body;
monitoring of the
development of excess
pore water
pressure in the loadbearing
part of the
foundation; monitoring
of subsidence
and tilting of the
foundation body.
- Pile driving log/pile
driving report, manufacturing
report regarding
in-situ concrete
piles;
- Eventual deformation
measurements,
as far as is reasonable;
- Eventual excess
pore water pressure
measurements, as
far as is reasonable;
Monitoring in the construction
phase
Supporting documents
to be submitted
in connection
with the inspection
documents:
- Reports of findings
and assessments in
the context of
Standard Design
audited by an
inspector
Operations
Operations,
maintenance
and monitoring
- Monitoring structural
behaviour under
working loads;
- It should be made
possible to be able
to take countermeasures
in good
time against behaviours
which differ
from those in the
design.
- Monitoring sediment
dynamics in the cable
route corridors
within and outside
the windfarm.
- Deformation measurements
on selected
offshore
structures within the
offshore wind farm;
- Monitoring scour at
regular intervals on
each foundation
Operations monitoring
(geotechnical monitoring)
Supporting documents
to be submitted
in connection
with the inspection
documents:
- Reports of findings
and assessments
audited by an inspector
3 Provisions
This guideline describes the minimum requirements of the Federal Maritime and Hydrographic
Agency in its role as an approval authority regarding geotechnical surveys and investigations
as well as field and laboratory studies including geotechnical assessments as part of the
design basis for the structural components of an offshore wind farm as well as monitoring
construction and operations. In this respect the present guideline is based on the Standard
Design which conforms to Eurocode (EC) and the codes of practice set out in DIN. With regards
to subsoil, EC 7 (DIN EN 1997-1 and DIN EN 1997-2) with national annexes and supplementary
guidelines (DIN 1054 and DIN 4020 in particular, with their normative references)
are decisive. Technical codes of practice, standards, guidelines etc., which are referred to by
this standard are valid in their most current version.
Geotechnical surveys and investigations must be coordinated with the planned foundation
concept, where on the one hand the difficulties regarding the foundation structure and also
the soil conditions and other boundary conditions on the other hand must also be properly
taken into account. It must always be carried out in such a scope that all characteristics of the
respective ground conditions can be established in good time before construction of the
structures.