Table 2:
Schematic representation of the time sequence for realisation of an offshore wind farm project
Phase
Measure
Responsible for the project
Certifier/ registered inspector
Approval authority
Development
Clarification of details
for the site
Geotechnical survey in accordance with
the BSH standard in its current version,
ascertaining meteorological and ocea
nographical parameters
Test report and certificate of con-
Planning with prelimi
nary draft of the instal
lation structure
Ascertaining the effects depending
on the planned offshore wind turbine,
preparation of the design basis and the
preliminary draft
formity for the design basis
Opinion on the preliminary draft
Inspection by the BSH *
1st release
Call for tenders
Compilation of the call for tenders docu
ments and evaluation
Design
Basic design
Calculation of definitive effects depend
ing on the selected system, definition
of the necessary certifications including
procedure, basic design and associated
calculations
Test reports and certificate of con
formity for the basic design
Inspection by the BSH *
2nd release (at least 1 year before
installation of the systems)
Implementation
planning
Undertaking of detailed calculations,
preparation of implementation docu
ments (drawings, specifications, etc.),
preparation of a logistics and decommis
sioning concept
Test reports for loading assumptions,
support structure, submarine cables,
transformer substation, measuring
mast, logistics and decommissioning
concept, etc.
Certificate of conformity for the site-
specific design evaluation
Inspection by the BSH *
3rd release
Implementa
tion
Production
Manufacture of all components of the
offshore wind farm on land
Inspection reports and certificate of
conformity for production monitoring
Transport
Land and sea transport from the produc
tion site to the planned installation site
Inspection reports and certificate of
conformity for transport monitoring
Installation
Erection and installation of all elements
of the offshore wind farm **
Inspection reports for erection and
installation monitoring
Commissioning
Commissioning of all elements of the
offshore wind farm
Inspection reports for commissioning
monitoring
Application for operating permit
Certificate of conformity for the in
stallation and commissioning moni
toring
Project certificate
Inspection by the BSH *
operations release (with con
straints if necessary)
Operation
Operation, mainte
nance and monitoring
Management of maintenance and repair,
logs, reports and evaluations, with any
necessary measures
Recurrent tests, inspection reports
and certificates of conformity
Inspection by the BSH *
upholding or temporary withdrawal
of the operating permit
Decommis
sioning
Decommissioning
planning
In good time before completion of the
operating phase, undertaking calcula
tions, preparing the implementation
documents for the selected decommis
sioning, updating the decommissioning
conceptts
Test report for the decommissioning
plan
Inspection by the BSH *
approval (possibly with constraints)
Undertaking the
decommissioning
Implementation of the planned measure
with detailed checking and monitoring to
accompany the decommissioning
Inspection reports and certificate of
conformity for the decommissioning
Inspection by the BSH * declara
tion of completion of the measure
by the BSH
**
Inspection by the BSH, if necessary with the involvement of a specifically engaged assessor,
i.e. offshore wind turbine, cabling within the wind farm, submarine cables, transformer substation and other elements